Unlicensed Electricity Generation Process (For Turkey)

01

01
Application

02

02
Commission Document Evaluation

03

03
Commission Technical Evaluation

04

04
Approval of the General Directorate of Energy Affairs

05

05
Call Letter Notification

06

06
Project Presentation to Authorized Institution

07

07
Project Approval (180 Days)

08

08
Project Approval Extension of Additional 180 Days (Electricity Distribution Company)

09

09
Connection Agreement

10

10
Power Plant Installation LV: 1 year - MV: 2 year MV HPP: 3 year

11

11
Central acceptance

12

12
System Usage Agreement 30 days